Priority Date : 2/19/1969
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
GROUND WATER
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
GROUND WATER
51N
04W
9
0
NE
SW
KOOTENAI
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
IRRIGATION
04/15
10/15
0.58 CFS
87.00 AFA
TOTAL
0.58 CFS
87.00 AFA
Places of Use
Place of Use Legal Description : IRRIGATION (KOOTENAI county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
51N
04W
9
NE
NW
39.0
51N
04W
9
NW
NW
32.0
51N
04W
9
SW
NW
39.0
51N
04W
9
SE
NW
40.0
51N
04W
9
NE
SW
39.0
51N
04W
9
NW
SW
40.0
51N
04W
9
SW
SW
40.0
51N
04W
9
SE
SW
39.0
51N
04W
16
NE
NW
7.0
51N
04W
16
NW
NW
30.0
Irrigation Totals
Total Acres
Acre Limit
345.00
29.00
Conditions
Code
Condtions
C18
This partial decree is subject to such general provisions necessary for the definition of the rights or for the efficient administration of the water rights as may be ultimately determined by the Court at a point in time no later than the entry of a final unified decree. Section 42-1412(6), Idaho Code.
C03
Right includes accomplished change in point of diversion pursuant to Section 42-1425, Idaho Code.
C05
Right includes accomplished change in place of use pursuant to Section 42-1425, Idaho Code.
K06
This right is limited to the irrigation of 29 acres within the place of use described above in a single irrigation season.
E51
Right Nos. 95-7044 and 95-2147 are limited to a total combined diversion rate of 4.42 cfs.
E55
Right Nos. 95-2147 and 95-7044 are limited to the irrigation of a combined total of 345 acres in a single irrigation season.
PIN
Parcel Nos. H00000096500 & H00000162700.
S40
The use of water for irrigation under this right may begin as early as March 15 and may continue to as late as November 15, provided other elements of the right are not exceeded. The use of water before April 15 and after October 15 under this remark is subordinate to all water rights having no subordinated early or late irrigation use and a priority date earlier than the date a partial decree is entered for this right.
P34
The remainder of this right was not claimed in the Coeur d Alene-Spokane River Basin Adjudication.