Priority Date : 10/22/1980
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
SHINGLE CREEK
SOUTH FORK
SHINGLE CREEK
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
SHINGLE CREEK
23N
01W
2
0
SE
NE
IDAHO
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
POWER
1/01
12/31
4.44 CFS
3214.00 AFA
TOTAL
4.44 CFS
3214.00 AFA
Places of Use
Place of Use Legal Description : POWER (IDAHO county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
23N
01W
1
SE
NW
Conditions
Code
Condtions
C18
This partial decree is subject to such general provisions necessary for the definition of the rights or for the efficient administration of the water rights as may be ultimately determined by the Court at a point in time no later than the entry of a final unified decree. Section 42-1412(6), Idaho Code.
08A
This right is subject to the provisions of Sections 42-205 through 42-210, Idaho Code, restricting the sale, transfer, assignment, or mortgage of this right. Failure to comply with these provisions is cause for immediate cancellation of this right.
01C
A flow measurement port or other device as specified by the Department shall be installed by the right holder to provide for the installation of measuring equipment and the determination of the rate of diversion by the Department.
R22
The rights for the use of water confirmed in this license shall be junior and subordinate to all rights for the use of water other than hydropower, within the State of Idaho that are initiated later in time than the priority of this right and shall not give rise to any right or claim against any future rights for the use of water, other than hydropower, within the State of Idaho initiated later in time than the priority of this right.
025
This right does not constitute Idaho Public Utilities Commission or Federal Energy Regulatory Commission approval that may be required.
The diversion and use of water for hydropower purposes under this license is subject to review by the Director on or after September 30, 2017, the expiration date of the power purchase contract with Idaho Power. The license is also subject to review by the Director after the date of expiration of license 4025-000 issued by the Federal Energy Regulatory Commission. Upon appropriate findings relative to the interest of the public, the Director may cancel all or any part of the use authorized herein and may revise, delete or add conditions under which the right may be exercised.
Facility known as Shingle Creek Project.