Priority Date : 2/7/1969
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
GROUND WATER
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
GROUND WATER
03N
02E
12
0
SE
SE
ADA
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
IRRIGATION
04/01
11/01
0.06 CFS
18.00 AFA
TOTAL
0.06 CFS
18.00 AFA
Places of Use
Place of Use Legal Description : IRRIGATION (ADA county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
03N
02E
12
SE
SE
4.0
Irrigation Totals
Total Acres
Acre Limit
4.00
Conditions
Code
Condtions
R69
This right when combined with all other rights shall provide no more than 0.03 cfs per acre nor more than 4.5 afa per acre at the field headgate for irrigation of the lands above.
X61
The period of use for the irrigation described in this approval may be extended to a beginning date of 3/1 and an ending date of 11/15 provided that beneficial use of the water can be shown and other elements of the right are not exceeded. The use of water before 4/1 and after 11/1 is subordinate to all water rights having no subordinated early or late irrigation use and a priority date earlier than 5/16/2008.
This right authorizes diversion from an existing well for shallow ground water that is not considered tributary to the Boise River. This right does not authorize construction of a new well, or enlargement or deepening of the existing well, that would intercept shallow ground water considered tributary to the Boise River.
103
When ordered by the Director, the right holder shall provide mitigation acceptable to the Director to offset depletion of lower Snake River flows needed for migrating anadromous fish. The amount of water required for mitigation, which is to be released into the Snake River or a tributary for this purpose, will be determined by the Director based upon the reduction in flow caused by the use of water pursuant to this right. Any order of the Director issued in accordance with this paragraph shall be in conformance with applicable rules allowing the right holder due process as the need for mitigation and the amount of mitigation are determined.