Priority Date : 2/24/1976
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
GROUND WATER
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
GROUND WATER
06N
03W
36
0
SE
SW
GEM
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
IRRIGATION
04/15
09/01
0.20 CFS
170.10 AFA
TOTAL
0.20 CFS
170.10 AFA
Places of Use
Place of Use Legal Description : IRRIGATION (GEM county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
06N
03W
36
NE
SW
26.0
06N
03W
36
NW
SW
11.8
Irrigation Totals
Total Acres
Acre Limit
37.80
Conditions
Code
Condtions
C18
This partial decree is subject to such general provisions necessary for the definition of the rights or for the efficient administration of the water rights as may be ultimately determined by the Court at a point in time no later than the entry of a final unified decree. Section 42-1412(6), Idaho Code.
S39
The use of water for irrigation under this right may begin as early as March 1 and may continue to as late as November 15, provided other elements of the right are not exceeded. The use of water before April 15 and after September 1 under this remark is subordinate to all water rights having no subordinated early or late irrigation use and a priority date earlier than the date a partial decree is entered for this right.