| Code |
Condtions |
| X35 |
Rights 36-2089 and 36-10852 when combined shall not exceed the total instantaneous diversion of water from all points of diversion of 4.98 cfs, nor a total annual maximum diversion volume of 1700.0 af at the field headgate, and the irrigation of 425.0 acres. |
|
Rights 36-2089, 36-10852, 36-2105A, 36-2342A, 36-2538A, and 36-7823A when combined shall not exceed a total diversion rate of 11.52 cfs, a total annual maximum diversion volume of 3024.0 af at the field headgate, and the irrigation of 756 acres. |
| F06 |
Rights 36-2089, 36-10852, 36-2105A, 36-2342A, 36-2538A and 36-7823A are diverted through the point(s) of diversion in the SWNESW of Section 16 and the NESWNE & SENWSE of Section 17, T08S, R26E. The new point of diversion in the NWNENW Section 16, T08S, R26E may only be used under Right Nos. 36-2089 and 36-10852. |
| R05 |
Use of water under this right will be regulated by a watermaster with responsibility for the distribution of water among appropriators within a water district. At the time of this approval, this water right is within State Water District No. 130. |
| R02 |
A lockable device subject to the approval of the Department shall be maintained on the diverting works in a manner that will provide the watermaster suitable control of the diversion. |
| 131 |
Prior to the diversion and use of water under Transfer approval 75076, the right holder shall install and maintain acceptable measuring device(s), including data logger(s), at the authorized point(s) of diversion and in accordance with Department specifications, or shall obtain an approved variance from the Department to determine the amount of water diverted from power records or to maintain an existing measuring device. |
| R64 |
This right when combined with all other rights shall provide no more than 0.02 cfs per acre nor more than 4.0 afa per acre at the field headgate for irrigation of the lands above. |
| 004 |
This right does not grant any right-of-way or easement across the land of another. |
| 046 |
Right holder shall comply with the drilling permit requirements of Section 42-235, Idaho Code and applicable Well Construction Rules of the Department. |
| T07 |
The right holder shall accomplish the change authorized by this transfer within one (1) year of the date of this approval. |
| T08 |
Failure of the right holder to comply with the conditions of this transfer is cause for the Director to rescind approval of the transfer. |
| T19 |
Pursuant to Section 42-1412(6), Idaho Code, this water right is subject to such general provisions necessary for the definition of the rights or for the efficient administration of water rights as may be determined by the Snake River Basin Adjudication court at a point in time no later than the entry of the final unified decree. |