Priority Date : 9/3/1976
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
GROUND WATER
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
GROUND WATER
02S
35E
32
0
NW
NE
BINGHAM
GROUND WATER
02S
35E
32
0
NW
NE
BINGHAM
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
DOMESTIC
01/01
12/31
0.25 CFS
28.80 AFA
TOTAL
0.25 CFS
28.80 AFA
Places of Use
Place of Use Legal Description : DOMESTIC (BINGHAM county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
02S
35E
32
NW
NE
02S
35E
32
SW
NE
Conditions
Code
Condtions
WB4
The total instantaneous diversion of water from all points of diversion under Rights 35-7639 shall not exceed 0.25 cfs, nor total combined annual volume of 28.8 af.
Prior to the diversion and use of water under Transfer approval 70081, the right holder shall install and maintain acceptable measuring device(s), including data logger(s), at the authorized point(s) of diversion, in accordance with Department specifications.
X36
Right 35-9067 is also diverted through the point(s) of diversion described above.
X62
The quantity of water decreed for this water right for domestic use is not a determination of historical beneficial use.
X63
All water rights within Basin 35 are from connected sources of water in the Snake River Basin and shall be administered conjunctively.
046
Right holder shall comply with the drilling permit requirements of Section 42-235, Idaho Code.
Domestic use is for 25 homes within Idle Wheel Mobile Estates, Parcel Number RP0344500.
T07
The right holder shall accomplish the change authorized by this transfer within one (1) year of the date of this approval.
T08
Failure of the right holder to comply with the conditions of this transfer is cause for the Director to rescind approval of the transfer.
T19
Pursuant to Section 42-1412(6), Idaho Code, this water right is subject to such general provisions necessary for the definition of the rights or for the efficient administration of water rights as may be determined by the Snake River Basin Adjudication court at a point in time no later than the entry of the final unified decree.