Priority Date : 1/27/1976
Basis : Decreed
Status : Active
Water Source
Source
Source Qualifier
Tributary
Tributary Qualifier
GROUND WATER
Points Of Diversion (Location)
Source
Township
Range
Section
Govt. Lot
QQQ
QQ
Q
County
Diversion Type
GROUND WATER
09N
42E
20
0
SW
NW
FREMONT
Water Uses
Beneficial Use
From
To
Diversion Rate
Volume
IRRIGATION
04/01
10/31
0.02 CFS
3.50 AFA
TOTAL
0.02 CFS
3.50 AFA
Places of Use
Place of Use Legal Description : IRRIGATION (FREMONT county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
09N
42E
20
SW
NW
1.0
Irrigation Totals
Total Acres
Acre Limit
1.00
Conditions
Code
Condtions
R63
This right when combined with all other rights shall provide no more than 0.02 cfs per acre nor more than 3.5 afa per acre at the field headgate for irrigation of the lands above.
201
Any future action following the approval of transfer 76808, including a subsequent transfer of this right or an order rescinding a transfer approval, which would result in a change to the point(s) of diversion under this right may require mitigation for the effects of the change. Such future action to change the point(s) of diversion under this right shall be analyzed for effects to connected reaches of the Snake River based on the priority date, point(s) of diversion and steady-state quantity as authorized for this right.
01M
After specific notification by the Department, the right holder shall install a suitable measuring device or shall enter into an agreement with the Department to use power records to determine the amount of water diverted and shall annually report the information to the Department.
004
This right does not grant any right-of-way or easement across the land of another.
T07
The right holder shall accomplish the change authorized by this transfer within one year(s) of the date of this approval.
T08
Failure of the right holder to comply with the conditions of this transfer is cause for the Director to rescind approval of the transfer.
T19
Pursuant to Section 42-1412(6), Idaho Code, this water right is subject to such general provisions necessary for the definition of the rights or for the efficient administration of water rights as may be determined by the Snake River Basin Adjudication court at a point in time no later than the entry of the final unified decree.