Water Right Report : 2-2001-B ( Decreed/Active)

Water Right Owners

Owner Type Name Address City State Postal Code
Attorney MARTEN LAW LLP PO BOX 2139 BOISE ID 83701-2139
Current Owner STATE OF IDAHO TRUSTEE PO BOX 83720 BOISE ID 83720-0010
Present Owner IDAHO POWER COMPANY PO BOX 70 BOISE ID 83707-0070

Water Right Status

Priority Date : 7/2/1908
Basis : Decreed
Status : Active

Water Source

Source Source Qualifier Tributary Tributary Qualifier
SNAKE RIVER COLUMBIA RIVER

Points Of Diversion (Location)

Source Township Range Section Govt. Lot QQQ QQ Q County Diversion Type
SNAKE RIVER 07S 13E 2 8 SW SW TWIN FALLS
SNAKE RIVER 07S 13E 2 7 SE SW GOODING

Water Uses

Beneficial Use From To Diversion Rate Volume
POWER 01/01 12/31 1300.00 CFS
TOTAL 1300.00 CFS

Places of Use

Place of Use Legal Description : POWER (GOODING county)
Township Range Section Lot QQQ QQ Q Acres
07S 13E 2 7 SE SW

Conditions

Code Condtions
162 Power generation is at the Lower Salmon Falls Power Plant.
1. Legal title to this water right is held in trust by the State of Idaho, by and through the Governor, for the benefit of Idaho Power Company as the user of the water for power purposes and for the benefit of the people of the State of Idaho. In addition to the subordination to the water rights defined in paragraph nos. 4 and 5 below, this water right shall be subject to subordination to and depletion by any other water right acquired pursuant to applicable state law, unless such other water right is unlawfully exercised or depletes or will deplete the average daily flow of the Snake River below 3900 CFS from April 1 to October 31 or below 5600 CFS from November 1 to March 31 as measured at the "Murphy Gaging Station" described below in paragraph no. 2. Average daily flow, as used herein , shall be based upon actual flow conditions; thus, any fluctuations resulting from the operation of Idaho Power Company facilities shall not be considered in the calculation of such flows. Flows of water purchased, leased , owned or otherwise acquired by Idaho Power company from sources upstream of its power plants, including above Milner Darn, and conveyed to and past its plants below Milner Dam shall be considered fluctuations resulting from the operation of Idaho Power Company facilities . Fluctuations resulting from Idaho Power's operations are the sole exclusion to the rule that all flows actually present at the Murphy Gaging Station constitute actual flow conditions. Flows of water purchased, leased, owned or otherwise acquired by other entities are not considered fluctuations.
2. The "Murphy Gaging Station" (U.S. Geological Survey gage no. 13172500) is located on the right bank of the Snake River at river mile 456.8, approximately B .5 miles east­ northeast of Murphy, Idaho and 0.9 miles downstream from the Swan Falls power plant at latitude 43° 15' 17.33" N, longitude 116° 23' 26.30" W, North American Datum of 1983, in the NW ¼ of the NW ¼ of section 18, T.2S., R.lE., Boise Meridian, Hydrologic Unit 17050103. 3. Idaho Power Company, as user of the water for power purposes and a beneficiary of the trust referenced above, is entitled to use the water available at the facility identified herein to the extent of its actual beneficial use but not to exceed the "QUANTITY" set forth above, and to protect its rights to such use of the water as provided by state law against depletions or claims not in accordance with state law. 4. This water right is subordinate to the lawful exercise of water rights of those persons dismissed from Idaho Power Co. v. State of Idaho, Case No. 81375 (Fourth Judicial Dist. Feb. 16, 1990). (A list of the original dismissed water right holders is made part of the record in SRBA consolidated Subcase No. 00-92023. The list does not reflect subsequent changes to the original water rights resulting from transfers, splits and renumbering.) 5. This water right is subordinate to all water rights diverting water from the Snake River and surface and groundwater sources tributary to the Snake River, with a priority date senior to October 25, 1984, unless otherwise indicated on the face of individual water rights. 6. For the purposes of the determination and administration of this water right, no portion of the waters of the Snake River or surface or ground water tributary to the Snake River upstream from Milner Dam shall be considered. This water right may not be administered or enforced against any diversions or uses of the waters identified in this paragraph. 7. This partial decree is consistent with the Swan Falls Agreement dated October 25, 1984, the Contract to Implement Chapter 259, Sess. Laws, 1983 dated October 25, 1984 and the Consent Judgments entered in Ada County Civil Cases Nos. 62237 (Mar. 9, 1990) and 81375 (Feb. 16, 1990). The Swan Falls Agreement dated October 25, 1984, shall not be merged into nor integrated with this partial decree, but shall remain in full force and effect independent of this partial decree.
C18 8. This partial decree is subject to such general provisions necessary for the definition of the rights or for the efficient administration of the water rights as may be ultimately determined by the Court at a point in time no later than the entry of a final unified decree. Section 42-1412(6), Idaho Code.
Dates
  • Licensed Date :
  • Decreed Date : 8/16/2017
  • Permit Proof Due Date :
  • Permit Proof Made Date :
  • Permit Approved Date :
  • Permit Moratorium Expiration Date :
  • Enlargment Use Priority Date :
  • Enlargement Statute Priority Date :
  • Application Recevied Date:
  • Protest Deadline Date:
Other Information
  • State or Federal : S
  • Water District Number : 02
  • Generic Max Rate Per Acre : 0
  • Generic Max Volume Per Acre : 0
  • Civil Case Number :
  • Decree Plantiff :
  • Decree Defendant :
  • Swan Falls Trust or Nontrust :
  • Swan Falls Dismissed :
  • DLE Act Number :
  • Cary Act Number :
  • Mitigation Plan: False