Water Right Report : 11-7406( License/Active)

Water Right Owners

Owner Type Name Address City State Postal Code
Current Owner STATE OF IDAHO IDAHO WATER RESOURCE BOARD CYNTHIA BRIDGE CLARK PO BOX 83720 BOISE ID 83720-0098

Water Right Status

Priority Date : 5/13/1993
Basis : License
Status : Active

Water Source

Source Source Qualifier Tributary Tributary Qualifier
BEAR LAKE BEAR RIVER

Points Of Diversion (Location)

Source Township Range Section Govt. Lot QQQ QQ Q County Diversion Type
BEAR LAKE 15S 44E 16 0 SW NE BEAR LAKE

Water Uses

Beneficial Use From To Diversion Rate Volume
LAKE LEVEL MAINTENANCE 1/01 12/31
TOTAL

Places of Use

Conditions

Code Condtions
027 Use of water under this right shall be non-consumptive.
Use of water under this right shall recognize and allow the continued beneficial diversion of water for irrigation or other purposes under any prior existing water right established by diversion and application to beneficial use or by an application, permit, or license on file or issued by the Director under the provisions of Chapter 2, Title 42, Idaho Code, with a priority of water right date earlier than May 13, 1993, the priority date of this right. Upon a future finding and order of the Director that gauging stations are required to maintain the approved minimum lake level, such measuring devices shall be permanently installed and maintained as specified by the Director. This right establishes the minimum lake level of Bear Lake at 5902.0 feet. Bear Lake is located within T15S, R43E; T15S, R44E; T16S, R43E; and T16S, R44E. The location described as the point of diversion is the approximate location of the Lifton pumps at the Bear Lake outlet. The Director retains jurisdiction, as described below, to review and amend any and all parameters of this right. The Board, upon receiving a request, or upon its own initiative, may petition the Director for an amendment to the right. The petition must set forth any significant change in circumstances and evidence of the public interest supporting the proposed amendment. The Director will notify the general public and specific persons or known interested parties of the proposed change, and conduct a hearing for the purpose of determining whether the right should be amended in the public interest. The burden of proof at the hearing shall be upon the persons or parties seeking the amendment to establish that the amendment of the right would be in the public interest.
Dates
  • Licensed Date : 8/24/1995
  • Decreed Date :
  • Permit Proof Due Date : 3/1/1999
  • Permit Proof Made Date : 6/6/1994
  • Permit Approved Date : 11/10/1993
  • Permit Moratorium Expiration Date :
  • Enlargment Use Priority Date :
  • Enlargement Statute Priority Date :
  • Application Recevied Date: 5/13/1993
  • Protest Deadline Date:
Other Information
  • State or Federal :
  • Water District Number : 11
  • Generic Max Rate Per Acre : 0
  • Generic Max Volume Per Acre : 0
  • Civil Case Number :
  • Decree Plantiff :
  • Decree Defendant :
  • Swan Falls Trust or Nontrust :
  • Swan Falls Dismissed :
  • DLE Act Number :
  • Cary Act Number :
  • Mitigation Plan: False