Place of Use Legal Description : AESTHETIC STORAGE (ADA county)
Township
Range
Section
Lot
QQQ
QQ
Q
Acres
04N
01W
22
SW
NE
Conditions
Code
Condtions
26A
Project construction shall commence within one year from the date of permit issuance and shall proceed diligently to completion unless it can be shown to the satisfaction of the Director of the Department of Water Resources that delays were due to circumstances over which the permit holder had no control.
Water bearing zone to be appropriated is from 1 to 10 feet.
123
Water stored under this right is subject to fluctuations of the water table caused by changes in the flow of local streams and by diversions under prior ground water rights. This right does not guarantee the maintenance of any particular ground water level.
220
The pond established by storage of water under this right shall not exceed a total capacity of 12 acre-feet or a total surface area of 1.2 acres.
170
To mitigate for the depletion of water resulting from the use of water under this right and to prevent injury to senior water right holders, the right holder shall cease diverting and using water as authorized by the following water right for the purposes and amounts specified below. Moreover, the official record for the following water right will be changed to show that diversion and use of water is not authorized because the right, or portion thereof, is being dedicated to mitigation purposes.
Use Changed Mitigation Mitigation Mitigation
Right No. to Mitigation Rate (cfs) Volume (AF) Acres
63-145 Irrigation 0.02 4.2 1.2
The land that will no longer be irrigated under this right is located within the SWNE, Section 22, Township 4N, Range 1W, B.M.
If the specified mitigation right, or portion thereof, is sold, transferred, leased, used on any place of use, or is not deliverable due to a shortage of water or a priority call, then the amount of water authorized for diversion under this right approval shall be reduced by the same proportion as the reduction to the mitigation rights.
R05
Use of water under this right will be regulated by a watermaster with responsibility for the distribution of water among appropriators within a water district. At the time of this approval, this water right is within State Water District No. 63, Boise River.
X59
Point of diversion and place of use are located within a portion of Lot 1, Blk. 2, Spurwing Subdivision.
X01
Aesthetic Storage is for 1 pond at Spurwing Golf Course.
Water diverted for mitigation under right 63-145 shall be returned to the Boise River within the SESW, Section 13, T4N, R2W, B.M.